BBC 10 January 2012 Last updated at 15:15 GMT
HS2: High-speed rail network gets go-ahead
A £33bn high-speed rail network has been given the go-ahead by the government, despite strong opposition.
Phase one of HS2, between London and Birmingham, should be running by 2026, later extending to northern England.
Transport Secretary Justine Greening has announced extra tunnelling along the 140-mile (225km) first phase in response to environmental concerns.
She said it would create "jobs, growth and prosperity", but critics dispute projected benefits of up to £47bn.
Ms Greening called the line "the most significant transport infrastructure project since the building of the motorways".
The London to Birmingham link would be followed by a second phase of Y-shaped track reaching Manchester and Leeds by about 2033, she said.
A consultation on the second phase will begin in early 2014, with a final route chosen by the end of that year.
Travelling at speeds of up to 250mph, passengers will be able to commute from Birmingham to London in 45 minutes, reducing the journey time by almost half from one hour and 24 minutes.
A Birmingham to Leeds journey will be reduced from two hours to 57 minutes and a Manchester to London journey from two hours and eight minutes to one hour and eight minutes.
Connections to existing lines should then cut journey times between London, and Edinburgh and Glasgow, to three-and-a-half hours.
The first phase of HS2 will include a connection to Europe via the Channel Tunnel. On completion of HS2 the network will include a direct link to Heathrow.
"By following in the footsteps of the 19th Century railway pioneers, the government is signalling its commitment to providing 21st Century infrastructure and connections - laying the groundwork for long-term, sustainable economic growth," said Ms Greening.
The government estimates that the project could eventually result in 9 million road journeys and 4.5 million journeys by plane instead being taken by train every year.
"HS2 is therefore an important part of transport's low-carbon future," Ms Greening said.
There had been almost 55,000 responses to the consultation process on the project, which clearly "generates strong feelings, both in favour and against the scheme", the minister said.
She pledged a commitment to "developing a network with the lowest feasible impacts on local communities and the natural environment".
"I have been mindful that we must safeguard the natural environment as far as possible, both for the benefit of those enjoying our beautiful countryside today and for future generations."
Revisions to the route had halved the number of homes at risk, as well as reducing by a third the number due to experience increased noise, she said.
Changes to the plans, Ms Greening said, also meant that "more than half the route will now be mitigated by tunnel or cutting", including:
A longer tunnel through the Chiltern Hills from Little Missenden, Buckinghamshire, to the M25
A new 2.75-mile (4km) tunnel to avoid impacts on communities in Ruislip, north-west London
A longer covered cutting, known as a green tunnel, past Chipping Warden and Aston le Walls in Northamptonshire
A curve in the route to avoid heritage sites around Edgcote, Northants
Longer green tunnels at Wendover and South Heath, Bucks
The Department for Transport said that 22.5 miles of the first phase would now be enclosed in tunnels or green tunnels - up from 14.5 miles for the route that went to consultation - and a further 56.5 miles of cuttings would significantly reduce "visual and noise impact".
'Wealthy few'
Protest groups formed to oppose the scheme say the planned route crosses an area of outstanding natural beauty and it will damage the environment.
Adam Thomas, whose home in the Chiltern hills will make way for the rail route, said: "We're going to lose our home which we've spent so long building for ourselves. But I feel more sorry in a way for the country because it's such a colossal waste of money and it is genuinely is not needed."
Opponents have also challenged the government's economic argument, suggesting the costs will be greater while the economic benefits will be lower than forecast, and that the business case for HS2 is based on an overly-optimistic prediction of growth in demand for long-distance train travel.
"There is no business case, no environmental case and there is no money to pay for it," said Stop HS2 campaign co-ordinator Joe Rukin.
"It's a white elephant of monumental proportions and you could deliver more benefits to more people more quickly for less money by investing in the current rail infrastructure."
Craig Bennett, director of policy and campaigns at Friends of the Earth, said: "We need to revolutionise travel away from roads and planes, but pumping £32bn into high-speed travel for the wealthy few while ordinary commuters suffer is not the answer.
"High-speed rail has a role to play in developing a greener, faster transport system, but current plans won't do enough to cut emissions overall - ministers should prioritise spending on improving local train and bus services instead."
However, the plan would be welcomed by "businesses up and down the country", said John Longworth, director general of the British Chambers of Commerce.
"Britain cannot continue to 'make do and mend' when it comes to its substandard infrastructure. Fundamentally, our global competitiveness is at stake," he said.
Stephen Joseph, chief executive of Campaign for Better Transport, said: "We're pleased to see the government investing in rail, rather than roads and aviation, and acting on some of the local environmental concerns surrounding HS2."
But he went on: "The process for deciding on the London-Birmingham part of HS2 has been too narrow and people feel left out.
"In consulting on the lines north of Birmingham, the government needs to involve people earlier with greater discussion of alternative options, including ways rail investment can support low-carbon growth in the communities served, and also how any new lines will integrate with existing networks and improve local as well as long-distance transport."
Analysis
Richard Black
Environment correspondent, BBC News
Big infrastructure projects often carry potential for both environmental benefit and harm; and HS2 is no exception.
Wildlife groups have warned it could damage around 160 important wildlife sites, and the latest modifications to the route have done little to alter that picture.
Stephen Trotter, head of Warwickshire Wildlife Trust, told BBC News he was "very disappointed"; the much vaunted extra tunnels will do little, he said, and there's still "serious concern" about destruction to woodlands and other important habitats.
All this might be bearable for environmental groups if HS2 guaranteed a big win on carbon emissions; but it doesn't.
The government's own projections show it's not certain to reduce either flying or road use.
In any case, the trains will only be a green transport option if the electricity they use comes from low-carbon sources - which hangs on continuing government support for renewables and nuclear.
Anti-HS2 campaigners argue that improving existing lines could bring more certain environmental benefits much cheaper and much sooner.
Full text of Minister's statement
A new high-speed rail line between London and Birmingham has been approved by Transport Secretary Justine Greening. Here is her statement in full:
"The consultation High Speed Rail: Investing in Britain's Future was one of the largest national consultations ever undertaken by the Department for Transport.
54,909 responses were received, from individuals, businesses and organisations across the country. It is clear from the consultation that a national high speed rail network - High Speed 2 - generates strong feelings, both in favour and against the scheme.
Since becoming Secretary of State for Transport I have taken time to consider all aspects of the consultation proposals and the evidence arising from both consultation responses and further work undertaken or commissioned by my Department and HS2 Ltd. This statement summarises my decisions.
I have decided Britain should embark upon the most significant transport infrastructure project since the building of the motorways by supporting the development and delivery of a new national high speed rail network.
By following in the footsteps of the 19th century railway pioneers, the government is signalling its commitment to providing 21st century infrastructure and connections - laying the groundwork for long-term, sustainable economic growth.
High Speed 2 (HS2) is a scheme to deliver hugely enhanced rail capacity and connectivity between Britain's major conurbations. It is the largest transport infrastructure investment in the UK for a generation, and, with the exception of High Speed 1 (HS1), is the first major new railway line since the Victorian era.
The HS2 Y network will provide direct, high capacity, high speed links between London, Birmingham, Leeds and Manchester, with intermediate stations in the East Midlands and South Yorkshire.
There will also be direct links to Heathrow Airport and to the Continent via the HS1 line. It will form a foundation for a potentially wider high speed network in years to come.
HS2 will be built in two phases to ensure that the benefits of high speed rail are realised at the earliest possible opportunity. The line from London to the West Midlands and the connection to HS1 are expected to open in 2026, followed, in 2032-33, by the onward legs to Manchester and Leeds and the connection to Heathrow.
The capital cost at 2011 prices of building the complete Y network is £32.7bn. At present values, it will generate benefits of up to £47bn and fare revenues of up to £34 billion over a 60-year period.
The benefits of HS2 will extend beyond the network itself; links to current lines will enable direct trains to run to cities such as Liverpool, Newcastle, Glasgow and Edinburgh and, with long-distance services transferring to the new network, space will be freed up for new commuter, regional and freight services on other lines, opening up new opportunities for Britain's existing railways.
Links to key urban transport networks, such as Crossrail, will help to spread the benefits further still.
HS2 is entirely consistent with the Government's objectives for carbon emissions. Electrified rail is a comparatively low-carbon mode of transport, especially with the continued decarbonisation of the grid.
Speed increases power consumption, but also makes HS2 more attractive to those currently flying or driving. The faster journeys on HS2 - Edinburgh and Glasgow will be just 3.5 hours from London - could transfer around 4.5 million journeys per year who might otherwise have travelled by air and 9 million from the roads.
HS2 will also create more rail capacity on existing conventional speed lines for freight - removing lorries from our busy trunk roads. HS2 is therefore an important part of transport's low-carbon future.
In securing these benefits for our country, I am committed to developing a network with the lowest feasible impacts on local communities and the natural environment.
I have been mindful that we must safeguard the natural environment as far as possible, both for the benefit of those enjoying our beautiful countryside today and for future generations.
People living along the line of route highlighted particular concerns and provided constructive and thoughtful comments about the London to West Midlands route proposed at consultation.
Following careful study by my engineers I can announce a package of alterations to further reduce the route's impacts. The changes mean that more than half the route will now be mitigated by tunnel or cutting and there will also be a reduction in the impacts on people and communities, ancient woodlands and important heritage sites.
The changes include:
A longer, continuous tunnel from Little Missenden to the M25 through the Chilterns;
A new 2.75 mile (4.4 km) bored tunnel along the Northolt Corridor to entirely avoid major works to the Chilterns Line and impacts on local communities in the Ruislip area;
A longer green tunnel past Chipping Warden and Aston Le Walls, and to curve the route to avoid a cluster of important heritage sites around Edgcote; and
A longer green tunnel to significantly reduce impacts around Wendover, and an extension to the green tunnel at South Heath.
The revised route offers considerable improvements to communities, with the number of dwellings at risk of land take almost halving and the number experiencing increased noise levels reducing by a third.
Despite these improvements to limit the negative impacts of the line, HS2 will inevitably affect some homeowners, communities and businesses.
To help those affected, we will bring in a package of measures, which are over and above what affected homeowners are already entitled to under law.
These include:
A streamlined purchase scheme to simplify the statutory blight process for property owners;
A sale and rent back scheme to give homeowners within the safeguarded area more flexibility;
A streamlined small claims scheme for construction damage which will allow individuals and businesses who are entitled to compensation under existing law to claim it more quickly and simply;
A package of measures to reinforce confidence in properties above tunnels. Homeowners will be offered before and after surveys, a thorough assessment of the impact of similar tunnels, an explanation of the measures that will be taken to prevent perceptible vibration impacts, financial compensation for the compulsory purchase of subsoil, and a legally binding promise that HS2 will be permanently responsible for resolving any related settlement or subsidence issues; and,
A refreshed hardship-based property purchase scheme
Finally, we will work constructively with local authorities along the line of route to minimise the negative consequences of HS2 and maximise the benefits.
In November I announced the Triennial Review of HS2 Ltd, and in making my decision I have accepted the finding that HS2 Ltd is the appropriate body to continue undertaking this work.
Today I have presented to Parliament a full account of my decisions titled High Speed Rail: Investing in Britain's Future - Decisions and Next Steps.
My department has published a series of supporting documents which set out in further detail the basis on which I have reached my decisions."